Why not, on January 15, 2022, Rekind through this team again proved its competence and professionalism through the completion of the Reliability Run (RR) Test implementation stages.
RR Test is one of a series of Commissioning activities which is the obligation of the Contractor (Rekind-FE) in accordance with the Document Contract RD-EPC04-CON-0302-Technical Requirements in the geothermal project. The document states that the contractor must complete the RR Test for 30 days.
In this activity, the implementation of the RR Test starts from December 16, 2021 to January 15, 2022. “Thank God the RTR process ran optimally without any problems according to our expectations,” said Rekind’s Project Manager for the Rantau PLTP Project, Dedap Dwi Novianto.

If this stage has been completed, then it will enter the Substantial Completion Date (SCD) section, which means Rekind has completed all work, punchlists and documentation, to then get an SCD Certificate as the start date for calculating the warranty period for two years to the owner. which in this case PT Supreme Energy Rantau Dedap (SERD).